Aardvark144
Active Member
The article didn't give much away did it. Would there be anything in the image of a Mogami attached to the article?
Nup, another pic of the meko a200 further down the page.The article didn't give much away did it. Would there be anything in the image of a Mogami attached to the article?
Depends, LCM is reported to be delayed, civmec still working on opvs 3-6 aswell as the LCH from next year. Still have Austal pushing out 2 Evolved Capes a year too and the entire precinct needs major upgrades.If the speculation is correct that up to the first six could be bult offshore, there will be a lot of feathers ruffled in the land of oz.
If feathers are going to be ruffled because the number of foreign yard built vessels is increased, given the nominated Australian partner has a backlog, then there is a simple solution. That solution is to re-award either the LMV-M (LCM8 replacement) project or the LMV-H project to another Australian based builder. That would remove most of the backlog obstuction and perhaps penalise the Australian yard for non-performance. If that process isn't investigated then there is no grounds for people to be upset about having more of the "urgently needed" GPFs built overseas by a yard that can deliver on their contract.If the speculation is correct that up to the first six could be bult offshore, there will be a lot of feathers ruffled in the land of oz.
Birdon's original plan was to use Echo as the primary builder. They were then informed that Austal was the COA's preferred builder, we're still waiting for an agreement to be reached.If feathers are going to be ruffled because the number of foreign yard built vessels is increased, given the nominated Australian partner has a backlog, then there is a simple solution. That solution is to re-award either the LMV-M (LCM8 replacement) project or the LMV-H project to another Australian based builder. That would remove most of the backlog obstuction and perhaps penalise the Australian yard for non-performance. If that process isn't investigated then there is no grounds for people to be upset about having more of the "urgently needed" GPFs built overseas by a yard that can deliver on their contract.
Agree.If feathers are going to be ruffled because the number of foreign yard built vessels is increased, given the nominated Australian partner has a backlog, then there is a simple solution. That solution is to re-award either the LMV-M (LCM8 replacement) project or the LMV-H project to another Australian based builder. That would remove most of the backlog obstuction and perhaps penalise the Australian yard for non-performance. If that process isn't investigated then there is no grounds for people to be upset about having more of the "urgently needed" GPFs built overseas by a yard that can deliver on their contract.
But the Evolved Mogami is already in production, the A200 is not.Nup, another pic of the meko a200 further down the page.
Also says Mogami believed to be about 20% more expensive than the A200 and then a bunch of experts giving their opinion.
I wonder what the price difference is between a Arafura and an E Cape?Depends, LCM is reported to be delayed, civmec still working on opvs 3-6 aswell as the LCH from next year. Still have Austal pushing out 2 Evolved Capes a year too and the entire precinct needs major upgrades.
Current timeline
2025-2029 Arafura class x4
2025-2031 Evolved Cape class x11, (yet to be ordered but planned)
2025-2032 LCM x18
2026-2035 LCH x8
2029-? GPF x8
Precinct upgrades 2026-2029
But what's the through life costs of the two designs?Nup, another pic of the meko a200 further down the page.
Also says Mogami believed to be about 20% more expensive than the A200 and then a bunch of experts giving their opinion.
There are something's an aluminium hulled PB just can't do which required an ANZAC to stand in for them.I wonder what the price difference is between a Arafura and an E Cape?
With collectively around fifteen vessels ,is there still scope to push for more of a balance towards increased OPV numbers
This maybe possible if increased frigate build numbers are awarded overseas.
Regards S
Do you know if it is the Cost or Design thats causing the delay?Birdon's original plan was to use Echo as the primary builder. They were then informed that Austal was the COA's preferred builder, we're still waiting for an agreement to be reached.
True. Who knows…But what's the through life costs of the two designs?
Time and time again the higher sticker price ends up being better value for money.
Definitely a sales pitch that would appeal a Canadian pollie.True. Who knows…
Not sure I believe the Japanese reps when they say the Mogami was designed for a 40 year service life.