Ananda
The Bunker Group
- Thread Starter Thread Starter
- #3,461
It is going to be behind schedule as the 6 PAF NC212i contract and work order behind TNI-AU 9 NC-212i. TNI-AU all delivery for 9 Aircraft supposedly done this year. However by year end, only 7th delivered. The 8th schedulle by 1st quarter 2026 and the last one by first half. Pinoy order behind it, thus best prediction by later part of next year or a year behind schedulle.
DI officially call Covid as main reason of delay especially between 2021-2023 or first four of TNI-AU order. However by 5th order they also change to propeler to MTV-27 made by Germany MT Aero. This I suspect also contribute to some schedulle time adjustment.
DI officially call Covid as main reason of delay especially between 2021-2023 or first four of TNI-AU order. However by 5th order they also change to propeler to MTV-27 made by Germany MT Aero. This I suspect also contribute to some schedulle time adjustment.