Yes, it will take years to fix a problem made over the last 20 years, there is no fast way out of this messDire. Only 3 out of 3 Type 45s are available at any time so as far as principal surface combatants go, Blighty can barely muster up a decent force for any sustained operations.
It will have to be pushed, no way the replacement type 83 will be specced and built in timeYup, that takes us down to 5 Frigates - Westminster is a blow as she's had a lot of money spent on her for little return. We need a bipartisan permanent committee of some weight to steer ship building over various governments. The mess we're in here, well, the previous government could have staved it off in the 14 years they had to work with, but realistically, the Type 26 program was dragging its heels even before then.
I'd like to think we'll learn some lessons and not push the OSD for Type 45 to the right but...well, yeah, as if.
As most would know it takes time to build a ship.Yup, that takes us down to 5 Frigates - Westminster is a blow as she's had a lot of money spent on her for little return. We need a bipartisan permanent committee of some weight to steer ship building over various governments. The mess we're in here, well, the previous government could have staved it off in the 14 years they had to work with, but realistically, the Type 26 program was dragging its heels even before then.
I'd like to think we'll learn some lessons and not push the OSD for Type 45 to the right but...well, yeah, as if.
The lack of F35s? to be honest I think that there are enough now (47 frames in total) for one carrier fully loaded or two decently partially populated. The real problem is weapons integration, which is dependant on software and hardware upgrades, Lockheed Martin are a serious gating factor in delivering capability here, buying more now delivers airframes but not more capability, and those airframes would need updating before they could deliver those capabilities, better to hold off now and place orders once block 4 capability is actually deliverable in my opinion.As most would know it takes time to build a ship.
The UK also has some social challenges with a greater number of the population feeling some economic pain.
While still an economically rich nation the pollies will reflect on the above.
Frigates, destroyer and subs are not a priority for many.
A shrunken fleet and carriers without a complete air wing are the result.
No easy fix for today and the immediate future even with regards as to the increased perception of threat and need.
They are in a bad spot.
Cheers S
Interesting take on the numbers.The lack of F35s? to be honest I think that there are enough now (47 frames in total) for one carrier fully loaded or two decently partially populated. The real problem is weapons integration, which is dependant on software and hardware upgrades, Lockheed Martin are a serious gating factor in delivering capability here, buying more now delivers airframes but not more capability, and those airframes would need updating before they could deliver those capabilities, better to hold off now and place orders once block 4 capability is actually deliverable in my opinion.
Impossible to know, but continuing to purchase machines that will need some very expensive upgrades to deliver what we actually want isn't the best idea in the world, again, in my opinion.Interesting take on the numbers.
I wonder if block 4 had been reached earlier if the UK would have in fact have increased the numbers of aircraft.
Both A and B models.
Cheers S
They'd had their planned lives extended quite some time ago, but they're not lasting until the new planned dates. I don't know whether it's lack of maintenance, overwork, or just unreality when setting the new retirement dates.It was pretty inevitable and entirely to be expected as the previous government waited and waited and waited before ordering new ship, the 23s couldn't be kept going any longer
![]()
Interesting but not unexpected.
Ships are harder to build when you dont maintain the capability to design and build. Also, minimum change never is, it just means you are hoping your technical risks dont evolve into technical debt, i.e. stuff you need to fix late in the program, because somebody early in the program said it would be ok.
Why not order a batch 2 of the T31s, which should reduce the capital cost and would allow for an increase in the fleet as well. A "Lite" version would probably not be as beneficial as a standard version. OPEX might be slightly lower but the operational flexibility would also be lower.From what I'm reading, Babcock are taking the cost on the chin so it's not pushing the price of the order north.
Out of sequence build errors do seem to be endemic in first of class construction and I'm told something similar happened with the carriers.
What happens next is going to be interesting in that the River batch 1s are all going out of service in 2028 or so. I'm wondering if ordering a diet lite spec of type 31 to replace one or two of the batch 1s would be feasible?